• JOHOR, Malaysia
  • Storage tanks and Silos
  • Post-Tensioning – Storage tanks and Silos

RGT–2 LNG Terminal

2015 – 2017

Successful collaboration on three LNG tanks in Singapore led EPCC contractor Samsung C&T to select VSL again as its partner, this time for work on a new LNG terminal project in Malaysia. The VSL project team was responsible for the construction of the outer containments of two 200,000m3 LNG tanks, including the operation of two sets of formwork, the prefabrication and installation of reinforcement and cast-in mechanical components, the supply and installation of post-tensioning and the placement of concrete.