• Krupa, Czech Republic
  • Bridges
  • Post-Tensioning – Bridges

D6 Krupá Highway Bridge

2024

As part of the D6 motorway linking Prague to Germany’s western border, the new Krupa highway bridge was key to improving regional traffic. The 830-metre-long concrete structures were built in situ and required extensive post-tensioning. VSL’s expertise guaranteed the structural integrity and long-term durability of the twin bridges. Despite tight deadlines, each of the 23 spans was successfully completed within just two weeks as required by the programme.