• Singapore, Singapore
  • Bridges, Viaducts and Footbridges
  • Repairs and preservation
  • Deconstruction & Replacement for Bridges, Viaducts and Footbridges

Upper Bukit Timah Bridge

2025

VSL replaced 38 bearings on a 1960s reinforced concrete highway bridge in Upper Bukit Timah, Singapore, under live traffic conditions and with limited working space. The team developed a custom jacking system, supported by purpose-built temporary steel brackets, and completed the full bearing replacement in only two days, saving two weeks against the original programme.

Upper Bukit Timah Bridge
  • Low-Carbon Solution